Data center zoning regulations (Case No. 25-LDC-0014)
Louisville is writing its first real rules for data centers after a nearly million-square-foot facility slipped in before any regulation existed. Experts warned about low-frequency noise that can pierce walls and triggered a federal class action against Microsoft in Wisconsin, plus rising power demand and water use. The committee is weighing whether to apply uniform performance standards, keep the 500,000-square-foot ban, and require a new dedicated zoning district with rezoning and a conditional use permit.
Data center regulations (LDC Text Amendment 25-LDC-0014)
Rules for the booming data center industry were formally introduced and sent to the Planning and Zoning Committee. Speakers want strong protections on electric rates, water use, noise, and renewable energy.
Temporary moratorium on data centers and telecom hotels
After a year of public pressure over the Campground Road hyperscale data center, the council passed a six-month moratorium on new data center applications and closed a loophole covering repurposed buildings. An attempt to extend it to a full year failed 10-15, and critics say the fight isn't over until permanent regulations pass.
FY 2026-27 Operating Budget
The council locked in next year's property tax rate. Your rate actually drops slightly — your bill goes up only because home values are up, and the total take is capped at a 4% increase by state law.
FY 2026-2027 Metro Budget
The next fiscal year's operating and capital budget ordinances, plus Louisville Tourism and TARC budgets, were introduced and sent to the Budget Committee — the decisions that set tax rates, services and construction projects for the year.
Powerhouse/Campground Road hyperscale data center
Speakers flagged enormous water demands for cooling — potentially tens of millions of gallons per day across facilities — and grid strain, noting one proposed West Louisville facility's 400 megawatts could equal the power needs of hundreds of thousands of homes.
FY 2026-27 Capital Budget
The next fiscal year's operating and capital budget ordinances, plus Louisville Tourism and TARC budgets, were introduced and sent to the Budget Committee — the decisions that set tax rates, services and construction projects for the year.
FY 2026-2027 Recommended Executive Budget
First readings of the operating and capital budget ordinances, plus Tourism and TARC budgets, set up the coming year's spending.