Campground Road data center

Summary not yet generated for this topic.

Community sentiment

Opposed (3)

At a glance

Public comments
3
Last 30 days
0

Last discussed Jul 27, 2026.

Public comments (3)

OpposedCatherine OvertonJul 27, 2026

A 72-year-old on fixed income living near the Campground Road site feared property value losses, cited LG&E's $11/month rate increase request, and asked for a moratorium.

Planning Commission — July 27, 2026 · 45:04 →
OpposedKenya (last name not stated)Jul 27, 2026

Called it 'rich' that the commission holds this hearing after approving the Campground Road center, accused the mayor of using the process to protect a friend's investment, and cited a survey in which 80% opposed data centers anywhere in Jefferson County.

Planning Commission — July 27, 2026 · 59:09 →
OpposedCassie LittleJul 27, 2026

Lives 2.5 miles from the Campground Road center; worried about noise and vibration, said she can't get answers from the developer or the mayor, and asked for a moratorium including the project that 'slipped through.'

Planning Commission — July 27, 2026 · 1:02:19 →